Street Paving Scheduled

The Town’s paving contractor will be in Town beginning on May 13 to resurface a number of streets, as shown on the map below.

The resurfacing work on each street will take several days and will include:

  • Removing the top two inches of asphalt from the road surface,
  • Repairing the road base as needed, and
  • Resurfacing the road

“No Parking” signs will be posted in advance of the work.  These signs are the best indication of when the work will be done on each block.  The exact timing and schedule of the work will depend on the weather and how many repairs are needed to the road base.  The Town must restrict parking on the block to ensure that the crews will be able to access the road surface.

During the road repaving, it will be necessary to close the street when the contractor is working.  The Town cannot guarantee access to driveways during the day, so please make sure any cars that are needed during the day are moved to an adjacent street. Work hours are generally 7:00 a.m. to 5:00 p.m.  The street will be reopened at the completion of each day’s work.

The Town will use the "Town Crier" to send out frequent updates on the project and to notify the resident of any schedule changes. Project updates will also be posted on the Town website.  Thank you in advance for your patience during this project.  Please contact the Town Office if you have any questions.

Paving Schedule Updates: 

Monday 5/20:

  • Final paving of Leland Street from Oakridge Avenue to East Avenue
  • Final paving of Thornapple Street from Oakridge Avenue to dead end
  • Remove top layer of asphalt from Thornapple Street between Connecticut Avenue and Meadow Lane

Tuesday 5/21:

  • Reinstall speed humps on Leland Street between Oakridge Avenue and East Avenue
  • Make base repairs on Thornapple Street from Oakridge Avenue to dead end
  • Remove top layer of asphalt and make base repairs on Underwood Street between Connecticut Avenue and Meadow Lane

Wednesday 5/22:

  • Final paving of Thornapple Street and Underwood Street between Connecticut Avenue and Meadow Lane

Thursday 5/23:

  • Remove top layer of asphalt and make base repairs to 45th Street
  • Remove top layer of asphalt and make base repairs to 46th Street between Elm Street and Willow Lane

Friday 5/24:

  • Final paving of 45th Street (entire length) and 46th Street between Elm Street and Willow Lane

Paving Map 2019