Street Paving Schedule

The Town’s paving contractor is resurfacing a number of Town streets following the completion of the Washington Gas main replacement project. The current tentative schedule is below:

  • Lynn Drive - Paving canceled for June 11.  Expected to be done June 14-15
  • Chatham Road - June 14-15
  • Maple Avenue between Oakridge Lane and East West Highway - June 16-17

The project will take approximately one month in total and will include:

  • Removing the top two inches of asphalt from the road surface,
  • Repairing the road base as needed, and
  • Resurfacing the road

Each street segment should be completed in 2-3 days.  The exact timing and schedule of the work on each street will depend on the weather, and how many repairs are needed to the road base.  The Town must restrict parking on the street to ensure that the crews will be able to access the road surface.  “No Parking” signs will be posted in advance of the work. 

During the road repaving, it will be necessary to close the street when the contractor is working.  The Town cannot guarantee access to driveways during the day, so please make sure any cars that you will need during the day are moved to an adjacent street.  Work hours are generally 7:00 a.m. to 5:00 p.m.  The street will be reopened at the completion of each day’s work.

If you have not joined the Town listserv, the Town Crier, we encourage you to visit the Town website and join today.  During the project, we will use the Town Crier to send out periodic updates on the project and any schedule changes.  The No Parking signs will be updated as necessary.  Although we are sure that there will be some inconveniences for residents, we will do everything possible to mitigate them.  In advance, thank you for your patience during this project. Please contact me in the Town Office if you have any questions.


2021 Paving Map