Street Paving to Continue Next Week *Correction*
The Town’s paving contractor is scheduled to continue street repaving next week. A tentative schedule is below. Each day, the Town will update the work schedule via the Town’s email notification system and on the Town website, as weather and other factors can cause unforeseen delays.
During the work, the streets will be closed and vehicular access to and from homes where the paving work is being done will be restricted during the day. The streets will be reopened each night. Please follow all traffic controls and “No Parking” signs that are posted. Thank you in advance for your cooperation during this inconvenient, but necessary, work.
Tentative Paving Schedule – Week of May 20
Monday 5/20
• Final paving of Leland Street from Oakridge Avenue to East Avenue
• Final paving of Thornapple Street from Oakridge Avenue to dead end
• Remove top layer of asphalt from Thornapple Street between Connecticut Avenue and Meadow Lane
Tuesday 5/21:
• Reinstall speed humps on Leland Street between Oakridge Avenue and East Avenue
• Make base repairs on Thornapple Street between Connecticut Avenue and Meadow Lane
• Remove top layer of asphalt and make base repairs on Underwood Street between Connecticut Avenue and Meadow Lane
Wednesday 5/22:
• Final paving of Thornapple Street and Underwood Street between Connecticut Avenue and Meadow Lane
Thursday 5/23:
• Remove top layer of asphalt and make base repairs to 45th Street
• Remove top layer of asphalt and make base repairs to 46th Street between Elm Street and Willow Lane
Friday 5/24:
• Final paving of 45th Street (entire length) and 46th Street between Elm Street and Willow Lane
Please click here for more information and a map of the work. Please contact the Town Office at townoffice@townofchevychase.org or 301-654-7144 with any questions.
▼
Plain text message
Street Paving to Continue Next Week *Correction*
The Town’s paving contractor is scheduled to continue street repaving next week. A tentative schedule is below. Each day, the Town will update the work schedule via the Town’s email notification system and on the Town website, as weather and other factors can cause unforeseen delays.
During the work, the streets will be closed and vehicular access to and from homes where the paving work is being done will be restricted during the day. The streets will be reopened each night. Please follow all traffic controls and “No Parking” signs that are posted. Thank you in advance for your cooperation during this inconvenient, but necessary, work.
Tentative Paving Schedule – Week of May 20
Monday 5/20
• Final paving of Leland Street from Oakridge Avenue to East Avenue
• Final paving of Thornapple Street from Oakridge Avenue to dead end
• Remove top layer of asphalt from Thornapple Street between Connecticut Avenue and Meadow Lane
Tuesday 5/21:
• Reinstall speed humps on Leland Street between Oakridge Avenue and East Avenue
• Make base repairs on Thornapple Street between Connecticut Avenue and Meadow Lane
• Remove top layer of asphalt and make base repairs on Underwood Street between Connecticut Avenue and Meadow Lane
Wednesday 5/22:
• Final paving of Thornapple Street and Underwood Street between Connecticut Avenue and Meadow Lane
Thursday 5/23:
• Remove top layer of asphalt and make base repairs to 45th Street
• Remove top layer of asphalt and make base repairs to 46th Street between Elm Street and Willow Lane
Friday 5/24:
• Final paving of 45th Street (entire length) and 46th Street between Elm Street and Willow Lane
Please visit the Town website for more information and a map of the work. Please contact the Town Office at townoffice@townofchevychase.org or 301-654-7144 with any questions.
▼
SMS message
Corrected Street Paving Schedule now available. Contact the Town Office at 301 -654-7144 or townoffice@townofchevychase.org for more information.